Boatnerd News – January 11, 2023

January 11, 2023

Soo Locks closing for seasonal repair, maintenance

SAULT STE. MARIE, Mich. – The Soo Locks in Sault Ste. Marie, Michigan will close to marine traffic beginning 11:59 p.m. January 15, or until commercial traffic ceases, through 12:01 a.m. March 25 to perform critical maintenance.

Federal regulation establishes the operating season based on the feasibility of vessels operating during typical Great Lakes ice conditions.

Every year, the Corps of Engineers uses the winter period to perform maintenance to keep the Soo Locks operating. The Detroit District team works long hours in extreme conditions to complete a significant amount of maintenance during this annual closure period. The work they perform is unique, especially given the harsh northern Michigan conditions they work in.

“Winter weather poses challenges and adds intensity to maintenance, the team is highly skilled and equipped to safely execute critical projects that allow for continued operational reliability,” LeighAnn Ryckeghem Soo Locks Operations Manager said.

The Corps of Engineers has several projects to complete before reopening the Poe Lock in March. The MacArthur Lock is scheduled to open April 24.

“This winter a portion of maintenance projects on Gate 1 require the Poe Lock to remain full while others require the lock to be dewatered,” Maintenance Branch Chief Nick Pettit said.  “Sequencing Poe Lock maintenance/repairs allows our team to maximize the non-navigation season.”

Dewatering of the Poe Lock will begin February 13. The MacArthur Lock will not be dewatered this year.

The team will install a temporary panel bridge across the Poe Lock. This panel bridge will provide the ability to mobilize materials and equipment to the job sites throughout the winter closure.

Maintenance crews will complete Gate 1 spring box and lever arm repairs to include replacing concrete, curtain bubbler replacement, Gate 1 lifting lugs, underfloor drain system inspection, dewatering chamber inspection/clean out, Gate 1 inspection for replacement, Gate 3 inspection for structural repairs, gate jacking pedestal inspections, valve repairs, Gate 1 turning feet, Gate 3 seal repairs and culvert intake grate repairs. The (miter) gates are the large gates serving as dams at each end of the lock chamber allowing the water to be raised and lowered in the chamber.

In addition to the above, crews also perform a wide range of other maintenance tasks from fender timber replacements on the piers to inspections and preventative maintenance on electrical and mechanical systems on both Poe and MacArthur Locks.

Contractors are currently working on the Poe Lock ship arrestor project. OCCI of Missouri, was awarded the contract in July 2021, for $17.5M after awarded options. This winter they are finishing the new downstream arrestor equipment buildings, installing the new arrestor machinery and replacing the arrestor boom.

The Corps of Engineers is building a second Poe-sized lock to provide much needed resiliency in the Great Lakes Navigation System. The second Poe-size lock, 110-feet by 1,200-feet, is being built on the existing Davis and Sabin Locks sites. The Davis Lock, which opened in 1914, has not been used since 2018, and only to transport Corps vessels. The Sabin Lock opened in 1918 and has been inactive since 1989. Both the Sabin and Davis Locks are too shallow for most modern vessels.

The Corps of Engineers contractor completed the first phase of construction, the upstream channel deepening was completed in August. The project’s second phase to stabilize the existing upstream approach walls wrapped up the second year of construction. The contractor installed 26 coffer cells, completing all 52 and placed 31,000 cubic yards of concrete. The upstream approach walls work will resume in Spring 2023. The final phase of construction, constructing the lock chamber, was awarded July with mobilization taking place in October/November.

U.S. Army Corps of Engineers, Detroit District

 

Museum celebrates community with free admission

TOLEDO, Ohio – In the community improvement and service spirit of the Martin Luther King holiday, beginning Saturday, January 14, through Monday, January 16th, The National Museum of the Great Lakes will open their doors for FREE in recognition of the support visitors, members and community partners have shown over the years.

“We will be celebrating the re-opening after our annual cleaning shutdown as well as welcoming a new year with an extended weekend of FREE admission, ” shares National Museum of the Great Lakes Education and Visitor Experience Director Ellen Kennedy. “We love showing off our incredible facilities and couldn’t think of a better way to enter 2023 than offering this.”

The museum originally introduced Community Appreciation Days in 2021 after being inspired to give back to those who generously continued to support our mission with the onset of the pandemic. “We appreciate all the support our community provides and are always looking for ways to connect more people with Great Lakes history as well as say thank you,” adds Kate Fineske, the museum’s Senior Director of Institutional Advancement.

Museum admission is always free for members, with non-member museum-only admission ranging from $8 – 11. Over Martin Luther King Day weekend the museum will be open from 10 – 5 p.m. on Saturday and Monday and Noon to 5 p.m. Sunday with free admission for all visitors.

Although not required, individuals may reserve their free tickets by pre-ordering and scheduling their visit online at nmgl.org. For more information on visitation, visit us online or call 419-214-5000.

View the gallery to see the full flyer

NMOTGL